Forth crossing opening delayed by six months

Written by Andrew Whitaker on 8 June 2016 in News

MSPs told that opening of bridge across the Forth delayed by six months 

The opening of the new £1.35bn bridge across the Forth has been delayed by six months, MSPs have been told. 

Scotland’s economy secretary Keith Brown said the Queensferry Crossing will now open in May 2017.

Brown said the delay had been caused by "adverse weather conditions" in April and May, as he confirmed that the December 2016 deadline will not be met.

He said the delay was a "very recent development" caused by high winds earlier this year, in a statement to MSPs.


RELATED CONTENT 

Forth Road Bridge defects could not have been foreseen, committee concludes

Room for growth: overview of the Scottish economy


Brown said the contractor, Forth Crossing Bridge Constructors (FCBC), had advised Transport Scotland that it was unable to achieve a target opening date of December 2016.

However, Scottish Labour deputy leader Alex Rowley said the announcement “will be greeted with disappointment in Fife and beyond”.

Rowley, a Fife MSP, said: “As someone who has campaigned for a new crossing for decades I would say, whilst the delay is disappointing, we need to keep it in perspective and make clear this new bridge is good news for Fife, good news for the East of Scotland, indeed good news for the whole of the Scottish economy.

“That is why it is important that minsters do not announce unrealistic deadlines and it is crucial that there is full transparency in this project.”

Categories

Tags

Categories

Related Articles

MPs vote for third runway at Heathrow as SNP MPs abstain
26 June 2018

The Scottish Government had previously said it backed the expansion of Heathrow Airport

Brexit and Scotland's rural economy
21 June 2018

Concern over challenges faced by rural communities have been long-running, but with Brexit on the horizon, new ones have emerged

Related Sponsored Articles

Share this page